Building for Every Generation! | 574.773.0603

Build Log

The Journey Through the Building Process

Overall Job Completion

  • Overall Completion 10% 10%

Pre-construction Phase

  • First Visit 100% 100%
  • Site Visit 100% 100%
  • Sales 100% 100%
  • Health Permit (Septic and Well Permits) 100% 100%
  • Building Permit 100% 100%
  • Construction Preview 100% 100%

Utilities

  • Electric Application 0% 0%
  • Electrical Engineering Meeting 0% 0%
  • Natural Gas or Propane Application 0% 0%
  • Natural Gas Engineering Meeting 0% 0%

Construction Phase

  • 100% 100%
  • Escavation (Hole Dug) 100% 100%
  • Footers Poured 0% 0%
  • Foundation Poured (Walls) 0% 0%
  • Foundation Floor Poured (Garages and Basements Only) 0% 0%
  • Sill Plates Installed 0% 0%
  • Partial Back Fill 0% 0%
  • Egress Windows and Jackposts Ordered 0% 0%
  • House Set 0% 0%
  • Garage Build 0% 0%
  • Electrical Installed 0% 0%
  • Gas Installed 0% 0%
  • HVAC Installed 0% 0%
  • Plumbing Finished 0% 0%
  • Gutters Installed 0% 0%
  • Flatwork (Sidewalks, Porch Caps, and/or Driveway) 0% 0%

Fit & Finish

  • Marriage Line 0% 0%
  • Drywall Repairs 0% 0%
  • Fit & Finish 0% 0%

Aftermarket

  • 6 Months 0% 0%
  • 1 Year 0% 0%

Certificate of Occupancy

  • Electrical Inspection 0% 0%
  • Mechanical Inspection 0% 0%
  • Plumbing Inspection 0% 0%
  • Final Inspection 0% 0%

Progress Pictures

Notes

Update 10/13

Will be dug in the next few weeks by either Steve Curtis, Troy Wallace, or Ben Martin. Sarah sent foundation prints and permits earlier this week.

Questions, Comments, Praise – Anything In-Between